You may copy an existing labor schedule and update it as necessary.
To copy an existing labor schedule:
Select
Work > Work Orders.
Select the work order for which to copy a labor schedule, and then
click the
Schedule Labor tab.
Select the labor schedule to copy, and then click
Copy Schedule.
Note: The system automatically populates
Employee and
Activity-Trade with the
employee and activity-trade performing the work for the selected work order.
The system also populates
Act. Est. Hours with the
number of hours planned for the work order activity;
Act. Sched. Hours with
the number of hours scheduled for the work order activity; and
Act. Actual Hours with
the total hours booked to date for the work order activity.
Specify this information:
Employee
Specify the personnel to schedule to perform the work. The
system automatically populates the employee description to correspond with the
selected employee.
Scheduled Date
Specify the date on which to schedule the work. You cannot
schedule work for any date earlier than today’s date.
Scheduled Hours
Specify the estimated number of hours to complete the work.
The number of hours must be between 0 and 24.