Freezing and unfreezing activity schedules

Temporarily freeze a schedule to compare the actual work done against the work that you scheduled. Frozen activity schedules cannot be updated.

To freeze and unfreeze activity schedules:

  1. Select Work > WO Planning > WO Scheduling.
  2. Right-click on the form, and then choose Freeze/Unfreeze.
  3. Specify this information:
    Freeze/Unfreeze
    Select Freeze to freeze the schedule, or select Unfreeze to unfreeze the schedule.
    From Date/To Date
    Specify the starting and ending dates for the freeze period.
    Department
    Specify the department for which to freeze or unfreeze schedules.
  4. Click Submit.