Associating projects to capital planning requests

Create a project to associate to a capital planning request.

To associate a project to a capital planning request:

  1. Select Work > Capital Planning Requests.
  2. Select the capital planning request for which to associate a project, and then click the Record View tab.
  3. Click Create Project.
    The system automatically populates Capital Planning Request.
  4. Specify this information:
    Project
    Specify a unique code identifying the project, and then enter a description of the project in the adjacent field.
    Organization
    Specify the organization of the project.
    Parent Project
    Specify the parent project if applicable.
    Shutdown
    Specify a shutdown identification code to associate with the project if the project requires the shutdown of equipment.
    Status
    Select the status of the project.
    Note: All projects start with a Status of Awaiting Approval.
    Class
    Specify the class of the project. The system automatically populates Class Org.
    Coordinator
    Specify the employee code of the project coordinator.
    Estimated Start Date
    Specify the intended starting date for the project.
    Estimated End Date
    Specify the intended ending date for the project.
    Actual Start Date
    Specify the actual starting date for the project.
    Actual End Date
    Specify the actual ending date for the project.
    Current Budget
    Specify the total budget amount for the project. Budgets of child projects do not roll up to the budget of the parent project.
    Labor
    Specify the estimated internal labor costs.
    Stock Items
    Specify the estimated stock material costs.
    Services
    Specify the estimated services costs.
    Budget Date
    Specify the date the budget was established.
    Note: You must enter a Budget Date that is before or equal to the current date.
    Hired Labor
    Specify the estimated hired external labor costs.
    Direct Purchases
    Specify the estimated amount of money needed to purchase materials not normally stocked in house.
    Tool Cost
    Specify the estimated cost of the tools.
  5. Click Submit.