Editing consequences for functional failures

Edit consequences for previously defined functional failures or failure modes defined for an equipment as part of the RCM assessment or RCM analysis for that equipment.

  1. Select one of these options:
    • Equipment > Assets
    • Equipment > Positions
    • Equipment > Systems
    • Equipment > Setup > Locations
  2. Select the equipment for which to edit functional failure consequences, and then click the RCM tab.
  3. Click Edit Failure Consequences.
  4. Specify this information:
    Consequence
    Select the consequence for the functional failure.
    Consequence Cost
    Specify the monetary value of the consequence cost.
    Sequence
    Specify the sequence number for the consequence.
    Note
    Specify note details as necessary.
  5. Click Submit.