Planning labor for job plans

Plan the labor necessary to complete a job plan.

To plan labor for job plans:

  1. Select Work > WO Planning > Job Plans.
  2. Select the job plan for which to plan labor, and then click the Plan Labor tab.
  3. Click Add Labor Line.
  4. Specify this information:
    Trade
    Specify the trade for the labor.
    Estimated Hours
    Specify the hours estimated to complete the labor.
    People Required
    Specify the number of people required to complete the labor.
    Hired Labor
    Select to indicate that the labor for the job plan will be completed by an external source.
  5. Click Submit.